Maui Approved Minor Replacement CBOC (one stop shopping concept) Minor Project – Obligated $937,451.42

Maui Multi-Services Center (One-Stop):  A Land Donation Offer has been received from the State of Hawaii and has been approved by VA Central Office.  VA Contracting, VAPIHCS, and the State of Hawaii are working towards final award, projected to be in late FY17.  Thirty percent design of the new CBOC has been accomplished with a remaining design/build project to be completed by mid-FY19.  Activation is projected during late FY19.

Next Milestone:  Request for proposal (RFP) format for Design Firms to be completed not later than October 31, 2017.